- Major pieces of core equipment delivered by ship to voestalpine’s site in Linz, Austria
- Construction of 180-ton EAF Ultimate electric arc furnace is underway and progressing on schedule
- Key part of voestalpine’s greentec steel program for decarbonized steel production
In January 2024, voestalpine awarded Primetals Technologies a contract to supply and implement an EAF Ultimate electric arc furnace at its site in Linz, Austria. The project has now achieved an important milestone with the delivery by ship of several major pieces of core equipment to Linz, including the transformers, each weighing approximately 160 tons, and the electric arc furnace shell. Civil and construction work began in late 2024 and is progressing on schedule.
Austria’s Largest Green Initiative
greentec steel is the clear strategy of the globally leading steel and technology group voestalpine for the transformation of its steel production: in the first step of this phased approach, one electric arc furnace (EAF) powered by green electricity will be built at each of the sites in Linz and Donawitz, aiming to reduce CO2 emissions by 30 percent by 2029. This corresponds to annual savings of almost 4 million tons of CO2, or nearly 5 percent of national emissions. That makes greentec steel Austria’s largest climate protection program.
EAF Ultimate: Maximum Performance in Quantity and Quality
Powered by green electricity, the EAF in Linz will produce 1.6 million tons of steel annually and is scheduled for startup in the first half of 2027. Primetals Technologies is supplying the complete EAF Ultimate equipment, a dedusting system, a waste-heat recovery system, a power supply solution, and material handling for alloying materials and additives. The order also includes full Level 1 and Level 2 automation, a power supply system featuring a static synchronous compensator (STATCOM) for optimized grid stabilization, and the LiquiRob robotic system, as part of a wide array of automation solutions, enhancing efficiency and occupational safety.
The advanced Level 2 automation system will enable superior process control and allow for precise calculation of the plant’s carbon footprint.
Key Facts: EAF Ultimate at voestalpine in Linz
Heat size: 180 tons
Dimensions: 11 x 9 meters
Construction site dimensions: 100 x 60 x 56 meters (length, width, height)
プライメタルズ テクノロジーズ (Primetals Technologies)は本社を英国、ロンドンに置き、金属鉄鋼産業におけるエンジニアリング、プラント建設、およびライフサイクルサービスの提供を行うパイオニアかつ世界的リーダーです。 当社は電機、オートメーション、デジタライゼーション、及び環境の総合ソリューションを含めた技術、製品、サービスの一式を提供しており、 原材料から完成品まで鉄鋼のあらゆる分野を網羅するだけでなく、非鉄分野でも最新の圧延ソリューションをお届けします。 当社は三菱重工グループ100%出資によるグループ会社で、従業員数は全世界で約7,000人です。 詳しくは、下記URLより当社公式ウェブサイトをご覧ください。:primetals.com/ja